Work experience

March 2015 until now - TES for Alstom Plant Narva Power Station, Estonia

I&C Engineer, Alstom Plant, Narva Power Station

On Alspa P320 Distributed Control System 6 series:

Commissioning activities: IOs tests, function checks, design changes and support for troubleshooting and setting instruments.

In charge of the Boiler Protection System (ICS Triplex): maintenance of the system, design change.

Quality: Set up and implement a document database of all the software modifications done during commissioning.

December 2014 to January 2015 - TES for Alstom Power Haruvit Power Station, Israel

System Engineer, Alstom Power Automation & Controls, Haruvit Power Station

Two weeks mission on the Haruvit site. Reinstall from scratch and configure 14 stations for the 2 Units with new hard drives.

Restore HMI for commissioning activities.

Update the system to the last version.

August 2013 to December 2014 - TES for Alstom Power Medupi Power Station, South Africa

I&C Engineer, Alstom Power Automation & Controls, Medupi Power Station

Manage a loop checkers team to perform input-output tests from HMI to instruments and actuators.

Commissioning activities: prepare safety clearance of DCS equipments, clear punch items, make design changes...

Tests and modifications of the logic implemented in the DCS (function checks) for commissioning of several systems on boiler area (ID, FD, PA fans, BFO, BCPS, Mills, Burners, etc) in collaboration with the process contractor.

September 2012 to June 2013 - TES for Alstom Power Massy, France

System Engineer, Alstom Power Automation & Controls, Engineering Department

On Alspa P320 Distributed Control System 6 series:

Integrate the Narva (Estonia) platform for 5 months. Factory Acceptance Test passed.

Participate in integration of the Kusile (South Africa) platform during 3 months (September to December).

January 2011 to July 2012 - TES for EDF Le Havre Power Station, France

Project Engineer, EDF Thermal Engineering Center

Set up Quality-Cost-Delay indicators to enforce a project management system.

-Develop a Manning Schedule as a HR tool.

-Design a general schedule of projects using MS Project with delay indicators.

-Implement the budgetary dashboards of the service projects and participate to the provisional budgetary meetings and purchase committees.

Realize the contract follow-up of the technical assistance providers.

Develop the Quality notes of the Service.

2010 July to November - TES for Alstom Power Massy, France

Power Automation & Controls, Maintenance Department

Install, configure and realize maintenance of the Alspa P320 Distributed Control System 6 series on power plants under contract with Alstom.

Install the maintenance platforms of Terga (Algeria) and Fujairah (UAE) at Massy, France.

One month mission at Combigolfe (Fos-sur-Mer site): modify diagrams under Controcad to limit alarms occurrence.

2010 January to July - Ligeron for Renault Guyancourt, France

Chassis system engineering branch

In relation with suppliers and Renault specialists : management of dependability studies.

Identification and negotiation of the dependability requirements with suppliers in an international environment.

Realization of dependability studies (Functional Analysis, PRA, FMEA, FTA) and monitoring of the suppliers action plans.

2009 March to August - Final internship - Renault Guyancourt, France

Service of Incidentology Analysis

Development of processes related to the quality analysis activity on the chassis system department.

Animation of a working party; management of quality analysis; development of quality processes.

Benefit for the service :

Capitalization of the know-how, structuring of the activities, standardization and systematization of the delivered documents.

2008 May to August - Technical internship - Daimler-Benz Woerth factory (Germany)


Experimental measures and analysis on robots.

Measures of the torques and the currents of the driving motors to provide a diagnosis on the load, the vibration level and the brake efficiency.


ESTACA: Engineering school for transportation industry, Levallois-Perret, France

Master Degree, graduated in November 2009

Specialization : Mechatronics, Management of Technical Projects

Gustave Eiffel Lycee Bordeaux, France

Sciences and Technologies of the Industry Baccalaureate (passed with honours), graduated in 2003

Specialization : Electrotechnics